Proceedings of the 3rd Asia Pacific International Conference of Management and Business Science (AICMBS 2019)

Risk Analysis of Tower a Development in Surabaya “X” Project

Authors
Dewie Saktia Ardiantono, Nugroho Priyo Negoro, Aldia Wira Trispantia, Muhammad Ubaidillah Al Mustofa, Geodita Woro Bramanti
Corresponding Author
Dewie Saktia Ardiantono
Available Online 13 April 2020.
DOI
10.2991/aebmr.k.200410.014How to use a DOI?
Keywords
risk factor, risk mapping, AHP, risk mitigation
Abstract

The construction of Tower A in Surabaya’s “X” Project is one of the largest projects owned by PT X with a construction period of four years. The long period of development will certainly lead to various types of risks that can affect the development of the Surabaya “X” Project. This study aims to identify, assess, rank, and provide mitigation actions against risk factors that can affect the Surabaya “X” Project. This study uses a risk map method to conduct a risk assessment and analytical hierarchy process (AHP) to compare the weighting of each risk factor. Respondents in this study amounted to five informants from different team, consisting of the architect team, civil structure team, project operational controls (POP) team, mechanical, electricity, and plumbing (MEP) team, and site engineering manager team. The identification results obtained 41 risk factors, consisting of 11 risk factors in the architecture section, 11 risk factors in the civil structure, 6 risk factors in the POP section, and 13 risk factors in the MEP section. The results of the assessment and ranking obtained 26 risk factors that require risk mitigation actions, these risk factors consist of 11 factors part of the architecture, with priority being the delay in the completion of the design by the consultant. 6 factors are part of the civil structure, with priority being the mismatch of building structure design. 5 factors are part of the POP, with priority is the unavailability of cash flow. Lastly, the 4 factors of MEP part, with priority is the quality of material that is not according to the specifications. This research is expected to provide a reference material for owners of the “X” Surabaya Project in determining actions against each risk factor that can affect the project.

Copyright
© 2020, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Download article (PDF)

Volume Title
Proceedings of the 3rd Asia Pacific International Conference of Management and Business Science (AICMBS 2019)
Series
Advances in Economics, Business and Management Research
Publication Date
13 April 2020
ISBN
978-94-6252-954-0
ISSN
2352-5428
DOI
10.2991/aebmr.k.200410.014How to use a DOI?
Copyright
© 2020, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Cite this article

TY  - CONF
AU  - Dewie Saktia Ardiantono
AU  - Nugroho Priyo Negoro
AU  - Aldia Wira Trispantia
AU  - Muhammad Ubaidillah Al Mustofa
AU  - Geodita Woro Bramanti
PY  - 2020
DA  - 2020/04/13
TI  - Risk Analysis of Tower a Development in Surabaya “X” Project
BT  - Proceedings of the 3rd Asia Pacific International Conference of Management and Business Science (AICMBS 2019)
PB  - Atlantis Press
SP  - 85
EP  - 94
SN  - 2352-5428
UR  - https://doi.org/10.2991/aebmr.k.200410.014
DO  - 10.2991/aebmr.k.200410.014
ID  - Ardiantono2020
ER  -