Proceedings of the 2016 2nd International Conference on Education Technology, Management and Humanities Science

Research on Adjustment in Contract Sum Caused by Item Characteristic Discrepancy—Code of Bills of Quantities And Valuation for Construction Works 2013

Authors
Ze Chen, Hong Ke
Corresponding Author
Ze Chen
Available Online January 2016.
DOI
10.2991/etmhs-16.2016.35How to use a DOI?
Keywords
Item characteristic discrepancy; All-in unit rate; Adjustment in contract sum
Abstract

Item characteristic discrepancy can lead to readjustment of all-in unit rate. However, in the field of project management, the analysis of the determination of the new all-in unit rate is rare. So this paper aims to find the new ideas of determining the new all-in unit rate when item characteristics appear inconsistent. This study will be divided into the following steps. Firstly, three specific forms of item characteristic discrepancy will be determined by the analysis of relevant documents. According to three specific forms, the scope of the contract price adjustment will be defined; Secondly, the affecting factors of the new all-in unit rate will be analyzed, and then the new ideas of determining the new all-in unit rate will be offered. The new all-in unit rate which is caused by item characteristic discrepancy can be taken into account by learning from this study.

Copyright
© 2016, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Download article (PDF)

Volume Title
Proceedings of the 2016 2nd International Conference on Education Technology, Management and Humanities Science
Series
Advances in Social Science, Education and Humanities Research
Publication Date
January 2016
ISBN
10.2991/etmhs-16.2016.35
ISSN
2352-5398
DOI
10.2991/etmhs-16.2016.35How to use a DOI?
Copyright
© 2016, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Cite this article

TY  - CONF
AU  - Ze Chen
AU  - Hong Ke
PY  - 2016/01
DA  - 2016/01
TI  - Research on Adjustment in Contract Sum Caused by Item Characteristic Discrepancy—Code of Bills of Quantities And Valuation for Construction Works 2013
BT  - Proceedings of the 2016 2nd International Conference on Education Technology, Management and Humanities Science
PB  - Atlantis Press
SP  - 160
EP  - 165
SN  - 2352-5398
UR  - https://doi.org/10.2991/etmhs-16.2016.35
DO  - 10.2991/etmhs-16.2016.35
ID  - Chen2016/01
ER  -