The Application of Discounted Cash Flow and Real Option Analysis Methods for Coal Mining Projects with Abandonment and Expansion Options: A Case Study of Pt X in East Kalimantan, Indonesia

Authors
Efendi Sutrisno, Eka Pria Anas
Corresponding Author
Efendi Sutrisno
Available Online October 2019.
DOI
10.2991/aprish-18.2019.38How to use a DOI?
Keywords
Real Option Analysis, Discounted Cash Flow, Project Evaluation, Capital Budgeting
Abstract

Recent rising coal prices starting in the second half of 2016 has motivated both existing coal companies and new players to dig deeper to expand their production capacities and to explore new sites. This exposes them to higher risks. A tool that not only quantifies business opportunities but also takes into account uncertainty in coal projects becomes crucial. The traditional valuation method of discounted cash flow (DCF) analysis has been used for very long time but it is not sufficient for mining because it does not capture the high uncertainty and operational flexibility in the industry. An alternative valuation method, real option (RO) analysis can complement the limitations of DCF. Most studies related to RO Analysis application in mining project have focused on coal price and mining cost volatilities but none has examined the impact of foreign exchange rate volatility, especially the exchange rate between the US dollar (USD) and the Indonesian Rupiah (IDR) to the project value.This study aims to enrich the literature on RO analysis application using an Indonesian coal company as a case study. It shows that RO analysis improves decision making by taking into account uncertainty and management flexibility. Furthermore, this study examines how different volatilities impact project value. Besides price and cost volatilities studied previously, this study examines one additional parameter, the USD IDR exchange rate volatility, as well as how different option maturities affect project value. A case study analysis using quantitative method of project evaluation or capital budgeting is applied. Data are analyzed using descriptive and linear regression to form input parameters. First, DCF is applied; then, in order to capture uncertainty and management flexibility, RO Analysis is applied to complement the DCF method. This study confirms that RO Analysis improves decision making by accounting for uncertainty and management flexibility in the calculation. Volatility and option maturity are key parameters impacting the project value. The higher the volatility is, the higher the project value is. The longer the option life is, the higher the project value is.

Copyright
© 2019, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Download article (PDF)

Volume Title
Proceedings of the 3rd Asia-Pacific Research in Social Sciences and Humanities Universitas Indonesia Conference (APRISH 2018)
Series
Advances in Social Science, Education and Humanities Research
Publication Date
October 2019
ISBN
10.2991/aprish-18.2019.38
ISSN
2352-5398
DOI
10.2991/aprish-18.2019.38How to use a DOI?
Copyright
© 2019, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Cite this article

TY  - CONF
AU  - Efendi Sutrisno
AU  - Eka Pria Anas
PY  - 2019/10
DA  - 2019/10
TI  - The Application of Discounted Cash Flow and Real Option Analysis Methods for Coal Mining Projects with Abandonment and Expansion Options: A Case Study of Pt X in East Kalimantan, Indonesia
BT  - Proceedings of the 3rd Asia-Pacific Research in Social Sciences and Humanities Universitas Indonesia Conference (APRISH 2018)
PB  - Atlantis Press
SP  - 290
EP  - 300
SN  - 2352-5398
UR  - https://doi.org/10.2991/aprish-18.2019.38
DO  - 10.2991/aprish-18.2019.38
ID  - Sutrisno2019/10
ER  -