Abstract

Recently, as the problems such as lack of construction personnel and reduction of construction duration due to the increasing labor cost and aging labor personnel, the researches on the PC method have been reactivated. However, the purpose of most of these researches is to develop and structurally interpret the PC method, and there are not that many researches conducted from the perspective of the construction management. Accordingly, this research examines the composite method using hollow-PC column(hereinafter referred to as "HPC composite method") from the perspective of the construction management, and the purpose is to analyze the construction period of the HPC composite method. The differences per method are analyzed through the specific comparison of the construction procedures as well as the in-depth interview with the expert, and the construction period of the HPC composite method is analyzed based on the analyzed differences. It seems that the construction In the HPC composite method, the construction period seems to vary depending on the column segment status. It seems that the construction period can be more effectively shortened through increasing the number of segmented columns. However, since the construction period relating to work types other than the PC method is not considered in this research, it is necessary to analyze the construction period relating to the overall construction process in the future.

Copyright
© 2017, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Download article (PDF)

Volume Title
Proceedings of the 2016 International Conference on Architectural Engineering and Civil Engineering
Series
Advances in Engineering Research
Publication Date
December 2016
ISBN
10.2991/aece-16.2017.37
ISSN
2352-5401
DOI
10.2991/aece-16.2017.37How to use a DOI?
Copyright
© 2017, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Cite this article

TY  - CONF
AU  - Jaeyup KIM
AU  - Byeonghun PARK
AU  - Sooyeon SEO
AU  - Guncheol LEE
PY  - 2016/12
DA  - 2016/12
TI  - Construction Period Analysis of Composite Method Using Hollow-PC Column
BT  - Proceedings of the 2016 International Conference on Architectural Engineering and Civil Engineering
PB  - Atlantis Press
SP  - 163
EP  - 167
SN  - 2352-5401
UR  - https://doi.org/10.2991/aece-16.2017.37
DO  - 10.2991/aece-16.2017.37
ID  - KIM2016/12
ER  -