BIM Implementation for Temporary Medical Facility: A Case Study in Huoshengshan and Leishengshan Hospital in Wuhan
- DOI
- 10.2991/aebmr.k.220502.056How to use a DOI?
- Keywords
- Huoshenshan Hospital; Leishenshan Hospital; BIM technology; prefabricated building; Emergency Engineering Construction
- Abstract
In response to the novel Coronavirus outbreak in Wuhan, China, in early 2020, two new hospitals, Huoshenshan and Leishenshan, were established. However, traditional construction methods cannot meet the requirements of building in a short time. The construction of these two hospitals adopts the design and construction mode of prefabricated buildings combined with BIM technology. Based on reviewing the literature on the combination of these two technologies in recent years, this paper analyzes the unique advantages of BIM technology in each stage of assembly building construction by taking the construction process of Huoshenshan Hospital as an example. The aim is to provide experience and reference for the construction of temporary medical facilities in other countries and regions also suffering from the epidemic.
- Copyright
- © 2022 The Authors. Published by Atlantis Press International B.V.
- Open Access
- This is an open access article distributed under the CC BY-NC 4.0 license.
Cite this article
TY - CONF AU - Qi Hong PY - 2022 DA - 2022/05/16 TI - BIM Implementation for Temporary Medical Facility: A Case Study in Huoshengshan and Leishengshan Hospital in Wuhan BT - Proceedings of the 2022 International Conference on Urban Planning and Regional Economy(UPRE 2022) PB - Atlantis Press SP - 312 EP - 316 SN - 2352-5428 UR - https://doi.org/10.2991/aebmr.k.220502.056 DO - 10.2991/aebmr.k.220502.056 ID - Hong2022 ER -