Research on Cost Control Line of Overhead Transmission Line Projects in Chongqing
Authors
Guangjin Peng, Hui Zhu, Xiaorui Xing, Tingting Feng, Xuanhong Liang
Corresponding Author
Guangjin Peng
Available Online December 2016.
- DOI
- 10.2991/msota-16.2016.81How to use a DOI?
- Keywords
- overhead transmission line project; cost control line; clutering analysis; partial corelation analysis; support vector machine
- Abstract
Investment of Power transmission projects was always huge, and related to many complex factors. Preliminary design of the project in preparation stage plays a very important role in the project cost control. With the application of clustering theory, partial correlation analysis method and support vector machine theory, cost data learning problem of the overhead transmission line projects in Chongqing area was studied in this paper. The results show that the newly presented method to determine cost control line of overhead transmission line projects is scientific and reasonable.
- Copyright
- © 2017, the Authors. Published by Atlantis Press.
- Open Access
- This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).
Cite this article
TY - CONF AU - Guangjin Peng AU - Hui Zhu AU - Xiaorui Xing AU - Tingting Feng AU - Xuanhong Liang PY - 2016/12 DA - 2016/12 TI - Research on Cost Control Line of Overhead Transmission Line Projects in Chongqing BT - Proceedings of 2016 International Conference on Modeling, Simulation and Optimization Technologies and Applications (MSOTA2016) PB - Atlantis Press SP - 373 EP - 376 SN - 2352-538X UR - https://doi.org/10.2991/msota-16.2016.81 DO - 10.2991/msota-16.2016.81 ID - Peng2016/12 ER -