Claim Calculation of Multi-event Delay in International Project

Authors
Peng Zhang, Quan-Chen Gao, Shu-Liang Gao, Zhen-Li Hao, Yan-Ping Jiao
Corresponding Author
Peng Zhang
Available Online August 2015.
DOI
https://doi.org/10.2991/msmi-15.2015.67How to use a DOI?
Keywords
Construction delay, Construction clams, Multi-event delay.
Abstract
This paper defines the concept of construction time claim, and puts forward to analyze the claim procedure and claim processingmethod.Thepaper has carried on the quantitative analysis of multi-event delay, put forward the concept of effective claim time in the multi-events claim, then put forward the calculation method of construction claim and calculation steps.And it set up new parameters for the effective claim time, analyze the claim case, delimit claim responsibility and determine the claim values, finally propose the construction claim calculation based on the process delay of multi-event.
Open Access
This is an open access article distributed under the CC BY-NC license.

Download article (PDF)

Proceedings
2015 International Conference on Management Science and Management Innovation (MSMI 2015)
Part of series
Advances in Economics, Business and Management Research
Publication Date
August 2015
ISBN
978-94-62520-90-5
ISSN
2352-5428
DOI
https://doi.org/10.2991/msmi-15.2015.67How to use a DOI?
Open Access
This is an open access article distributed under the CC BY-NC license.

Cite this article

TY  - CONF
AU  - Peng Zhang
AU  - Quan-Chen Gao
AU  - Shu-Liang Gao
AU  - Zhen-Li Hao
AU  - Yan-Ping Jiao
PY  - 2015/08
DA  - 2015/08
TI  - Claim Calculation of Multi-event Delay in International Project
BT  - 2015 International Conference on Management Science and Management Innovation (MSMI 2015)
PB  - Atlantis Press
SN  - 2352-5428
UR  - https://doi.org/10.2991/msmi-15.2015.67
DO  - https://doi.org/10.2991/msmi-15.2015.67
ID  - Zhang2015/08
ER  -