Determiners of Schedule Delay Risk of the Highway Project in Vietnam: Based On the SEM model

Authors
Honganh Vu, Jianqiong Wang, Jicai Liu, Lianxing Min, Syhung Mai
Corresponding Author
Honganh Vu
Available Online January 2016.
DOI
10.2991/ifmeita-16.2016.19How to use a DOI?
Keywords
Construction Progress, Schedule Delays, Structural Equation Model, Risk Evaluation
Abstract

With the economic development of Vietnam in recent years, the highway construction develops rapidly and brings the international construction companies a good opportunity, but the phenomenon of schedule delays has a serious impact on the project investment efficiency, cost and reputation. In this paper, on the basis of former study and combining with interviews of Vietnam expert, we investigated the influential factors of highway construction schedule in Vietnam by the questionnaire survey in 2014, and evaluated the mutual influence of the above factors by using structural equation model (SEM). The empirical results showed that the 7 factors had significant impacts on the construction schedule delay. Finally, we propose the specific management sugges-tions to improve the international construction companies’ ability of risk management when partic-ipating in the highway project contract in Vietnam.

Copyright
© 2016, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Download article (PDF)

Volume Title
Proceedings of the 2016 International Forum on Management, Education and Information Technology Application
Series
Advances in Social Science, Education and Humanities Research
Publication Date
January 2016
ISBN
10.2991/ifmeita-16.2016.19
ISSN
2352-5398
DOI
10.2991/ifmeita-16.2016.19How to use a DOI?
Copyright
© 2016, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Cite this article

TY  - CONF
AU  - Honganh Vu
AU  - Jianqiong Wang
AU  - Jicai Liu
AU  - Lianxing Min
AU  - Syhung Mai
PY  - 2016/01
DA  - 2016/01
TI  - Determiners of Schedule Delay Risk of the Highway Project in Vietnam: Based On the SEM model
BT  - Proceedings of the 2016 International Forum on Management, Education and Information Technology Application
PB  - Atlantis Press
SP  - 98
EP  - 103
SN  - 2352-5398
UR  - https://doi.org/10.2991/ifmeita-16.2016.19
DO  - 10.2991/ifmeita-16.2016.19
ID  - Vu2016/01
ER  -