Analysis of Cost Control Process in PT. S’ Project Management on a 2018’s Work Package: Constructing a 100-Tonne-Capacity Integrated Cold Storage Facility in Kampar District
- DOI
- 10.2991/aebmr.k.210831.055How to use a DOI?
- Keywords
- cost control process, Kampar
- Abstract
Integrated Cold Storage facilities are much needed by the Indonesian Marine and Fisheries Ministry. The construction of ICS facility in Kampar District by PT. S in the fiscal year 2018 proved that effective project management (PM) must be implemented. One way to measure the performance of PT. S’ PM is by examining the control cost process throughout the project. Control costs is the process of monitoring the status of the project to update the project costs and managing changes to the cost baseline. Control cost process was analyzed using Earned Value Analysis. The results showed that PT. S’ PM faced many challenges in maintaining planned values. The result of this case study was presented to the company as an improvement tool for later projects.
- Copyright
- © 2021, the Authors. Published by Atlantis Press.
- Open Access
- This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).
Cite this article
TY - CONF AU - Sarah Shahnaz Ilma AU - Nofrisel PY - 2021 DA - 2021/09/02 TI - Analysis of Cost Control Process in PT. S’ Project Management on a 2018’s Work Package: Constructing a 100-Tonne-Capacity Integrated Cold Storage Facility in Kampar District BT - Proceedings of the 5th Global Conference on Business, Management and Entrepreneurship (GCBME 2020) PB - Atlantis Press SP - 285 EP - 290 SN - 2352-5428 UR - https://doi.org/10.2991/aebmr.k.210831.055 DO - 10.2991/aebmr.k.210831.055 ID - Ilma2021 ER -