Project Baseline Design for Scope, Time, and Cost Aspect in Putri Provinsi Multi Set Toys Book Project PT XYZ Bandung
- Keywords
- Project Management, beta distribution, CPM, bottom-up estimating, scope baseline, schedule baseline, cost baseline
- Abstract
PT XYZ is a company that has business units such as product publishing, book printing, distribution, television production houses, online stores, applications publishers, and digital media distribution. In 2017 PT XYZ is targeted to start a new product project, but not realized by the target. Based on the initial plan, this project should begin in June 2017, but in its implementation, the project implemented in September 2017. Based on the problems faced by the company on this project it is necessary to have a project baseline for the company so that the company can manage the project well and avoid the risk of project failure. The results of data processing obtained in aspect of scope, time, and costs are respectively Project Scope Statement, WBS, and WBS Dictionary (in terms of scope), the project schedule starts in September 2017 and ends in February 2021 (using beta distribution and CPM), also the estimate of project costs use bottom-up estimating for each workpackage
- Copyright
- © 2019, the Authors. Published by Atlantis Press.
- Open Access
- This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).
Cite this article
TY - CONF AU - Nurul Fitri AU - Devi Pratami AU - Wawan Tripiawan PY - 2019/07 DA - 2019/07 TI - Project Baseline Design for Scope, Time, and Cost Aspect in Putri Provinsi Multi Set Toys Book Project PT XYZ Bandung BT - Proceedings of the 5th Bandung Creative Movement International Conference on Creative Industries 2018 (5th BCM 2018) PB - Atlantis Press SP - 383 EP - 390 SN - 2352-5398 UR - https://www.atlantis-press.com/article/125910959 ID - Fitri2019/07 ER -