Cause Analysis and Treatment of Cracks in Bridge Pier under High Filling Soil
- DOI
- 10.2991/ifeesm-17.2018.325How to use a DOI?
- Keywords
- Bridge pier; High filling soil; Overloading effect; Cracks
- Abstract
A 30 m fabricated prestressed concrete simply supported T-beam bridge uses a pile foundation as its lower structure. Owing to the filled engineering spoil at the abutment side, which is higher than the original ground line 11.87 m, 8 cracks formed in the side of 3 pier columns adjacent to abutment within the range of 1 m above the filling line. According to the shape and location of the cracks, the corresponding calculation model is established by dividing the pier column into two sections of above and below the soil. The causes of the cracks formation and their influence on the structure are analyzed quantitatively. The correctness of the calculation model is verified by disease phenomena detected subsequently. Considering the poor stability of the filling soil, the spatula around the pier was stratified and cleaned, and then the crack was stable and the shear deformation of the support was basically restored.
- Copyright
- © 2018, the Authors. Published by Atlantis Press.
- Open Access
- This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).
Cite this article
TY - CONF AU - Qiang Liu AU - Bo Yu AU - Xianglin Jiang PY - 2018/02 DA - 2018/02 TI - Cause Analysis and Treatment of Cracks in Bridge Pier under High Filling Soil BT - Proceedings of the 2017 3rd International Forum on Energy, Environment Science and Materials (IFEESM 2017) PB - Atlantis Press SP - 1793 EP - 1797 SN - 2352-5401 UR - https://doi.org/10.2991/ifeesm-17.2018.325 DO - 10.2991/ifeesm-17.2018.325 ID - Liu2018/02 ER -