An Efficient Artificial Fish Swarm Model with Estimation of Distribution for Flexible Job Shop Scheduling

Authors
Hongwei Gehwge@dlut.edu.cn, Liang Sun*, liangsun@dlut.edu.cn, Xin Chenxinchendut@dlut.edu.cn, Yanchun Liangycliang@jlu.edu.cn
College of Computer Science and Technology, Dalian University of Technology, Dalian, 116023, China
Department of Computer Science and Engineering, Washington University in Saint Louis, Saint Louis, Missouri, 63130, USA
College of Computer Science and Technology, Dalian University of Technology, Dalian, 116023, China
College of Computer Science and Technology, Dalian University of Technology, Dalian, 116023, China
College of Computer Science and Technology, Jilin University, Changchun, 130012, China
*Corresponding author: College of Computer Science and Technology, Dalian University of Technology, Dalian, China. Tel: 86-41186980422, Email: liangsun@dlut.edu.cn
Corresponding Author
Received 5 November 2015, Accepted 27 May 2016, Available Online 1 September 2016.
DOI
10.1080/18756891.2016.1237190How to use a DOI?
Keywords
Flexible job shop scheduling; artificial fish swarm model; estimation of distribution; Friedman test and Holm procedure
Abstract

The flexible job shop scheduling problem (FJSP) is one of the most important problems in the field of production scheduling, which is the abstract of some practical production processes. It is a complex combinatorial optimization problem due to the consideration of both machine assignment and operation sequence. In this paper, an efficient artificial fish swarm model with estimation of distribution (AFSA-ED) is proposed for the FJSP with the objective of minimizing the makespan. Firstly, a pre-principle and a post-principle arranging mechanism that operate by adjusting machine assignment and operation sequence with different orders are designed to enhance the diversity of population. Following this, the population is divided into two sub-populations and then two arranging mechanisms are applied. In AFSA-ED, a preying behavior based on estimation of distribution is proposed to improve the performance of algorithm. Moreover, an attracting behavior is proposed to improve the global exploration ability and a public factor based critical path search strategy is proposed to enhance the local exploitation ability. Simulated experiments are carried on BRdata, BCdata and HUdata benchmark sets. The computational results validate the performance of the proposed algorithm in solving the FJSP, as compared with some other state of the art algorithms.

Copyright
© 2016. the authors. Co-published by Atlantis Press and Taylor & Francis
Open Access
This is an open access article under the CC BY-NC license (http://creativecommons.org/licences/by-nc/4.0/).

1. Introduction

The Flexible Job-shop Scheduling Problem (FJSP) is an extension of classical JSP for flexible production situation, which allows an operation to be processed by any machine from a given set. Generally, the FJSP can be divided into two sub-problems, i.e., the machine assignment problem that arranges each operation to a machine from a given set of alternative machines, and the operation sequence problem that determines the processing sequence of all operations to obtain a feasible schedule. It has been proved that FJSP is a strongly NP-hard problem1.

Many research efforts have focused on the development of efficient methods for FJSP. The first study was performed by Bruker and Schlie2 for two jobs FJSP, in which a polynomial graphical algorithm was developed. Then the researchers have concentrated on exact optimization techniques such as branch and bound3,4, dynamic programming5, and disjunctive graph representation6,7. However, since the FJSP is a strongly nondeterministic polynomial-time hard problem, only moderate-size instances of the problems can be solved within a reasonable time by exact techniques. On the one hand, the approximate and heuristic methods make a tradeoff between solution quality and computational cost. These methods include dispatching priority rules8, shifting bottleneck approach9, and Lagrangian relaxation10. More recently, with the emergence of new techniques from the field of artificial intelligence, much attention has been devoted to meta-heuristics. The tabu search (TS) has been widely used, such as Brandimart11, Mastrolilli and Gambardella12, Bozejko et al. 13 and Li et al. 14, while the genetic algorithm (GA) has also been examined to be an efficient method such as in Chen et al.15, Kacem et al.16, Pezzella et al. 17 and Gao et al.18 Besides, some other meta-heuristics have been employed for this problem such as simulated annealing (SA)1921, particle swarm optimization (PSO)2224, ant colony optimization (ACO)25, artificial neural network (ANN)26, and artificial immune system (AIS) 27.

Among the above algorithms, the meta-heuristics have acquired great achievements and become a popular tool for solving NP hard combinational optimization problems28. The artificial fish swarm algorithm (AFSA) proposed by Li 29 is a population-based meta-heuristic. It is insensitive to initial values, and possesses good performance such as fast convergence, high fault tolerance and robustness30. Thus it has gained an increasing study and wide applications such as multi-objective optimization31, job shop schedule problem32 and clustering problem33. Motivated by these perspectives, we propose an efficient artificial fish framework with estimation of distribution (AFSA-ED) for FJSP. Meanwhile, some oriented heuristic strategies are proposed and embedded in the framework to enhance the overall performance, which include the integrated initialization process, the pre-principle and post-principle arranging mechanisms, the attracting behavior, and the public factor based critical path search strategy. The proposed algorithm balances the global exploration ability and the local exploitation ability.

2. Flexible Job-shop Scheduling and Basic Artificial Fish Swarm Algorithm

2.1. Flexible Job-shop Scheduling Problem

The FJSP can be described as follows. There are n jobs J = {J1, J2,...,Jn} to be processed on m machines M = {M1, M,...Mm}. Each job Ji has ni operations {Oi,1, Oi,2,...,Oi,ni} to be processed according to a given sequence. Each operation Oi,j can be processed on any machine among a subset Mi,jM. The FJSP is to solve the assignment of machines and the sequence of operations to minimize a certain scheduling objective, e.g., the makespan of all the jobs (Cmax).

Moreover, the following conditions should be satisfied while processing. Each machine processes one operation at a given time. Each operation is assigned to only one machine. Once the process starts, it cannot be interrupt. All jobs and machines are available at the beginning. The order of the operations for each job is predefined and cannot be modified.

For explaining explicitly, an example of FJSP is shown in Table 1. There are 2 jobs and 4 machines, where the rows correspond to the operations and the columns correspond to the machines. Each element denotes the processing time of this operation on the corresponding machine, and the “-” means that an operation cannot be processed on the corresponding machine.

Job Operation M1 M2 M3 M4
J1 O1,1 3 5 - 6
O1,2 6 - 4 5
J2 O2,1 - 5 2 3
O2,2 1 1 5 3
O2,3 2 3 - 2
Table 1.

A sample instance of FJSP

2.2. Standard Artificial Fish Swarm Algorithm

The artificial fish swarm algorithm (AFSA) is a population-based optimization algorithm, which is inspired from fish swarm behaviors. In an AFSA system, each artificial fish (AF) adjusts its behavior according to its current state and its environmental state, making use of the best position encountered by itself and its neighbors. The optimization of artificial fish swarm algorithm is conducted by four behaviors, i.e., preying, swarming, following, and moving.

Suppose Xi = (x1,x2,...,xn) is the current position of artificial fish AFi; Yi = f(Xi) is the fitness function at position Xi. Visual is the visible distance of AF; try_number is the try times of preying behavior; Step is the maximum moving step of AF; δ is the crowd factor; nf is the number of AFs within its visual. For AFi, one target position Xj in its visual can be described by Eq. (1), Rand() is a function that generate random numbers in the interval [0,1]. Then the AFi updates its state by using Eq. (2) when the updating condition is satisfied.

Xj=Xi+visualRand()
Xi/next=Xi+XjXi||XjXi||StepRand()

The four behaviors of AF are described as follows:

  1. (1)

    Preying: The AFi chooses a position Xj randomly within its visible region using Eq. (1). If Yj < Yi, it moves one step to Xj according to Eq. (2). Otherwise, it chooses another position and determines whether it satisfies the requirement Yj < Yi. If the requirement is still not satisfied after try_number times, AFi executes the moving behavior.

  2. (2)

    Swarming: Suppose XC is the center position in the visible region, if the center has more food and low crowd degree as indicated by YC · nf < Yi · δ, then AFi moves a step towards XC according to Eq. (2). Otherwise, AFi executes default preying behavior.

  3. (3)

    Following: Suppose Xb is the best found position in the visible region, if the position Xb has high food consistence and low crowd degree as indicated by Yb · nf < Yi · δ, then AFi moves a step towards Xb according to Eq. (2). Otherwise, AFi executes default preying behavior.

  4. (4)

    Moving: AFi choose a random position in its visual region and moves a step towards this direction. It is a default behavior of preying.

In AFSA, swarming and following are simulated in each generation. The AFs will choose the behavior to find the position with better fitness value, and the default behavior is preying. The flow chart of AFSA is shown in Fig. 1.

Fig. 1.

The framework of basic AFSA

3. Artificial Fish Swarm Algorithm with Estimation of Distribution (AFSA-ED)

The main components of the proposed AFSA-ED include the following strategies. Firstly, the pre-principle and the post-principle arranging mechanisms are applied to adjust the machine assignment and the operation sequence. Secondly, the preying behavior based on estimation of distribution is imitated by an object-oriented probability model. Thirdly, the attracting behavior is applied to improve the global search ability of algorithm. And finally, the local search based on critical path is applied to balance exploration and exploitation.

3.1. Pre-principle and post-principle Mechanisms

The FJSP optimizes the objective function by adjusting the machine assignment and the operation sequence. The order of solving the two sub-problems may affect the optimal results. Thus, we propose a pre-principle arranging mechanism and a post-principle arranging mechanism to adjust machine assignment and operation sequence. The objective is to enhance the diversity of population and make the algorithm searching the feasible solutions more comprehensively. The proposed mechanisms work as follows:

  1. (1)

    Pre-principle arranging mechanism (PrA): The machine assignment part is firstly adjusted for balancing the workload of each machine, and then the operation sequence part is adjusted for minimizing the total makespan.

  2. (2)

    Post-principle arranging mechanism (PoA): The operation sequence part is firstly adjusted for balancing the completion time of each job, and then the machine assignment part is adjusted for minimizing the total workload of machines.

While implementing the AFSA, the population is divided into two sub-populations. The two sub-populations respectively adopts the PrA and PoA mechanisms. After the independent evolution for each sub-populations, they are recombined to an entire population for further evolution.

3.2. The preying behavior based on estimation of distribution

In an AFSA system, preying behavior usually tends to be blindfold since the selection of destination locations is achieved by a random process. To overcome this shortcoming, we propose to estimate the distribution of the individuals, and then use the distribution model to guide preying behavior. The estimation of distribution algorithm (EDA) can reduce the randomness of behavior and make the search move toward and converge to the promising regions in the solution space.

The EDA works as follows: (1) Select a set of promising individuals from the population according to the fitness value; (2) Estimate the probability distribution of the selected individuals according to a probabilistic model. The probability distribution is constructed by two matrixes, i.e., the machine probabilistic matrix and the operation probabilistic matrix; (3) Generate new individuals according to the estimated probability.

Let I denote the number of promising individuals selected from the current population, and D1l be the machine probabilistic matrix at the lth generation. Each entry dijkl of D1l means the probability of operation Oi,j being processed on machine Mk and it is determined by the following formula:

dijkl=aijkl/I
Where aijkl is the number of individuals that select Mk to process operation Oi,j.

Let D2l denote the operation probabilistic matrix at the lth generation. Each entry dijlof D2l means the probability of job Jj being arranged in position i in the operation sequence and it is calculated by the following formula:

dijl=aijl/I
Where aijl is the number of individuals arranging Jj in position i.

While implementing the preying behavior, a new individual is generated by sampling the two probabilistic matrixes. The machine assignment vector is generated through sampling the probabilistic matrix D1l. For each operation Oi,j, machine Mk is selected with a probability of dijkl. Similarly, the operation sequence vector is generated by sampling the probabilistic matrix D2l. Job Jj is selected with a probability of dijl to replace the j-th position of operation sequence vector.

3.3. Attracting behavior

In AFSA, each AF determines its next position according to current state and its environmental state within its visible region, which may limit the exploration ability and interaction with the other AFs outside its visible region. We propose an attracting behavior to enhance exploration ability.

The bulletin board that records the state of the current optimal individual is setup. For each AF, it reads the position information of the optimal individual from the bulletin board, and then it moves one step toward this direction.

Suppose Xi is the current position of AFi, Yi, is the fitness value. Xbest is the position of the global optimal individual and its fitness value is Ybest. If Yi > Ybest, then AFi, moves towards Xbest for a step according to Eq. (2). Otherwise, if Yi > Ybest, which means that it is the optimal individual, then it executes default preying behavior.

3.4. Critical Path Local Search based on Public Factor

In this subsection, a local search procedure is presented to enhance the exploitation around the best solution obtained by the AFSA. The local search is based on the critical path, so it is applied to the schedule represented by the disjunctive graph rather than by the AF. Hence, when a solution is to be improved by the local search, it should be firstly decoded to a schedule represented by the disjunctive graph.

3.4.1. The disjunctive graph

A feasible solution of FJSP can be represented by the disjunctive graph G = (N,BC), where N is a set of nodes which includes all the operations and two dummy nodes: starting and terminating; B is a set of conjunctive arcs which represents precedence constraints in the same job; C is a set of disjunctive arcs which correspond to the precedence of operations processed on the same machine. The weight of each node is the processing time of corresponding operation. In a disjunctive graph, the longest path form the starting node to terminating node is called critical path, whose length determines the makespan of the schedule. Any operation on the critical path is called critical operation.

Take the problem shown in Table 1 for instance, a possible schedule represented by the disjunctive graph is showed in Fig. 2. SG and EG are respectively dummy starting and terminating nodes. The operations O1,1 and O2,3 are performed on M1 successively, O2,1 and O1,2 are performed on M3 successively, and O2,2 is processed in M2.

Fig. 2.

Illustration of framework of disjunctive graph

3.4.2. Neighborhood structure based on public factor

The disjunctive graph usually has more than one critical paths. Only changing the length of all the critical paths, the makespan can be changed. For obtaining a better schedule from the current one, lots of operations may be tried to move. The process is time consuming. So the public factor based critical path search in the neighborhoods is proposed. The public factor is used to identify the influence degree of the critical for all the critical paths. The public factor of an operation Oi,j can be defined by the formula:

Pfi,j=Ni,j/Tcp
Where Tcp is the total number of critical paths, and Ni,j is the number of the critical paths including the operation Oi,j. Pfi,j is in the interval [0,1]. Pfi,j = 0 means this operation does not include any critical path, in other words, it is not a critical operation; Pfi,j = 1 means this operation is included in all critical paths. For each critical operation, the higher value of public factor one operation possess, the greater impact for disjunctive graph it has while moving it. In the neighborhood structure, the critical operation with the highest public factor will be moved preferentially.

While moving an operation, the precedence constrains should be satisfied. For an operation Oi,j processed on Mk, we define SEG(Oi,j) as the earliest start time and CEG(Oi,j) = SEG(Oi,j) + ti, j, k as the earliest completion time. Similarly, denote the latest start time without delaying the makespan as SLG(Oi,j) and the latest completion time as CLG(Oi,j) = SLG(Oi,j) + ti, j, k. Let PJi,j = Oi, j−1 be the precedent of operation Oi,j and FJi,j = Oi, j+1 be the successor of operation Oi,j. Denote PMi,j as the operation performed on Mk right before Oi,j and SMi,j as the operation performed on Mk right after Oi,j. In the disjunctive graph G, the process of moving an operation Oi,j is to delete it from its current machine sequence by moving all its disjunctive arcs and then insert it at another available machine by adding disjunctive arcs. Let POl (l = 1,2, ..., x) be the critical operation to be moved, where x is the total number of critical operations in G. Let G be the disjunctive graph obtained by deleting the critical operation POl from G. For no increasing the makespan after inserting operation POl, we take Cmax(G) as the makespan of G when we calculate the latest start time SLG (Oi,j) for each operation in G. If POl is inserted before Oi,j on machine Mk in G, it could be started as early as CEG (PMi,j) and should be completed as late as SLG (Oi,j) without delaying the required makespan Cmax(G). In addition, POl needs to comply with the operation precedence constraints. So, the available idle time for inserting POl to machine Mk need to satisfy the following condition:

max{CEG(PMi,j),CEG(PJPOl)}+tPOl,k<min{SLG(Oi,j),SLG(FJPOl)}

This moving process is repeated until a better schedule strategy is found or all critical operations have been tried to move. The procedure of local search is shown in Algorithm 1.

1. Convert the feasible schedule to the disjunctive graph G
2. Get all the critical operations in the G
3. Calculate the Pf of all the critical operations and sort them in descending order to form a set {PO1, PO2,...POx}
4. for i = 1 to x do
  Delete POi from G to get G
  Calculate all the idle time intervals in G
  if existing an available time interval for POi
  then
    Insert the operation POi to get Gi
    Return the disjunctive graph Gi
  end if
end for
5. Return the final disjunctive graph.
Algorithm 1.

The procedure of critical path local search

Figure 3 gives an illustration of the local search for the example in Table 1. In Fig. 3 (a), the only critical path is SGO1,1O2,1O2,2O2,3EG, and the makespan is 17. The critical operation set is POl = {O1,1, O2,1, O2,2, O2,3}, and all the public factors for the critical operations are 1. So we can try to move the critical operations O1,1, O2,1, O2,2, and O2,3 successively. In this process, the algorithm preferentially selects the machine with the least processing time is and then judges the feasibility according to Eq. (6). Fig. 3 (b) show the disjunctive graph G1 obtained by moving the critical operation O1,1 to machine M1. In this case, the makespan is reduced to 12. Fig. 3 (c) show the disjunctive graph G2 obtained by moving the critical operation O2,1 to machine M3. IN this case, the makespan is 11. Following this, the critical operation O2,2 is not satisfied the moving condition according to Eq. (6). Finally, the algorithm obtains the disjunctive graph Fig. 3 (d) by moving the critical operation O2,3 to machine M4. In this case, the makespan is reduced to 9.

Fig. 3.

Illustration of the local search

4. The Implementation of AFSA-ED for FJSP

In this section, we will give the implementation of the AFSA-ED for FJSP. Firstly, the representation of the AF, decoding method and the population initialization are introduced. Then, the framework of the algorithm is presented.

4.1. Representation and movement

In AFSA-ED, each AF represents a feasible solution of the problem. Each AF is expressed by two vectors: machine assignment vector and operation sequence vector, which correspond to the two sub-problems of the FJSP. The machine assignment vector is represented by a vector of N integer values and N is the total number of operations. Each element of vector denotes the machine selection of each operation and the value is the index of the array of alternative machine set. The operation sequence vector is an un-partitioned permutation with repetitions of job Ji (i = 1,2,...,n). The length of operation sequence vector equals to N. The index i of job Ji occurs ni times in the vector, and the k-th occurrence of a job number refers to the k-th operation in the technological sequence of this job.

For the problem in Table 1, a representation of a feasible solution is shown in Fig. 4. The machine assignment vector is (1,2,2,2,3). If the operation O2,1 is processed on {M2, M3, M4}, then the corresponding element ‘2’ means that operation O2,1 will be assigned to the second machine M3. If the operation sequence is given as (2,1,2,2,1), then scanning the vector from left to right, the processing order of operations can be obtained: O2,1O1,1O2,2O2,3O1,2.

Fig. 4.

Illustration of the representation of a solution

To address the discrete FJSP, the movement of an AF in the solution space is completed by learning the partial structure from the target AF. Fig. 5 gives an illustrative example of the movement process. Assume the i-th AF is (1,2,2,2,3;2,1,2,2,1) in the current generation, and its target AF is (2,2,1,3,2;1,2,2,1,2), then an indicator vector with the same length is produced by randomly filled with the elements of the set {0, 1}. The number of the element “1” is int[N2] in the first part of the indicator vector, whereas the second part of the indicator vector has only one position filled by “1”. The elements in the first part of the indicator vector decide the sources of the corresponding elements in new produced AF, namely from the parent or the target. The elements “1” in the second part of the indicator vector represents the starting position of the operation sequence segment from the target AF, and its length is also taken as int[N2], and the remainder is from the parent AF. Finally, m machine selections and operation orders are adjusted randomly according to the corresponding update formula, and m = int[step · rand()] as in the formula (2).

Fig. 5.

Illustration of the movement of an AF

4.2. Decoding of AF

For calculating the value of the makespan, each individual in the artificial fish swarm is decoded to the corresponding schedule sequence. The decoding is achieved by the process that assigns operations to the machines at their earliest possible starting time according to technological order of the jobs. It is worth noticing that the scheduling acquired in this way is semi-active. Then the active decoding is applied, which checks the possible blank time interval before appending an operation at the last position, and fills the first blank interval before the last operation to convert the semi-active schedule to an active one so that the makespan can be shorten34.

4.3. Initialization

In this subsection, an integrated initialization algorithm is proposed for machine assignment initialization and operation sequence initialization. To generate the initial machine assignments, the following rules are applied:

  1. (1)

    Global approach of localization (GAL)17.

  2. (2)

    Local approach of localization (LAL).

  3. (3)

    Random rule.

The LAL makes a random permutation for the positions of machines. Following this, for each operation, it selects the machine with minimum processing time in the alternative machine set, and updates the machine workload by adding this processing to the processing time of the remaining unarranged operations within the same job. Take the problem showed in Table 1 as an example, Table 2 shows a possible machine assignment obtained by using the LAL. The last four columns indicate the final assignments obtained by LAL. In the table, the items in bold type are the updated workload of machines, and the “-” means that the operation cannot be processed on the corresponding machine.

M3 M2 M4 M1 M3 M2 M4 M1 M3 M2 M4 M1 ... M3 M2 M4 M1
O1,1 - 5 6 3 - 5 6 - 5 6 - 5 6
O1,2 4 - 5 6 4 - 5 9 - 5 9 - 5 9
O2,1 2 5 3 - 2 5 3 - 2 5 3 - 5 3 -
O2,2 5 1 3 1 5 1 3 1 5 1 3 1 7 3 1
O2,3 - 3 2 2 - 3 2 2 - 3 2 2 - 4 2
Table 2.

Initial assignments by LAL

The random rule executes by randomly selecting a machine from the alternative machine set for each operation. The GAL emphasizes the global workload among all the machines. The advantage of the LAL is that it obtains different initial assignments in different runs of the algorithm and emphasizes the workload among the set of machines within the same job. In addition, the random rule can increase the diversity of initial population. In our algorithm, the above three rules are used in a hybrid way. More specially, the initial machine assignments of 30% solutions in the population are generated by the GAL, 50% solutions by the LAL, and 20% solutions by random rule.

In our algorithm, the initial operation sequences are generated by the following three dispatching rules:

  1. (1)

    Most time remaining (MTR). The job with the most remaining processing time will be arranged first.

  2. (2)

    Most number of operations remaining rule (MOR). The job with the most remaining unprocessed operations has a high priority to be arranged.

  3. (3)

    Random rule. Randomly generate the sequence of the operations. In particular, the above three rules are used in a hybrid way, then 20% of initial operation sequences are generated by random rule, 40% by the MTR, and 40% by the MOR.

4.4. The framework of AFSA-ED

The framework of AFSA-ED for solving FJSP is shown in Fig. 6. At the beginning of each generation, the entire population is randomly divided into two equal size sub-populations with one sub-population using machine based mechanism, and the other sub-population using operation based mechanism. Each AF evaluates by executing swarming, following, attracting behaviors. If the algorithm obtains a better solution using the three behaviors, it selects a better behavior to execute, otherwise, it executes the default improved preying behavior. When all individuals complete the searching process, the two sub-populations are combined into an entire population. Then the optimal individual of the population executes the critical path based on local search for further exploitation. If a new better individual is obtained, then the bulletin board is updated accordingly. The algorithm stops when the maximum iteration time is reached.

Fig. 6.

The framework of the AFSA-ED for the FJSP

5. Experimental Results

5.1. Instances and parameters

To evaluate the performance of the AFSA-ED, we consider three sets of well-known benchmarks with 160 instances:

  1. (1)

    BRdata: The data set includes 10 instances from Brandimarte11. The number of jobs ranges from 10 to 20, the number of machines ranges from 4 to 15, and the flexibility of each operation ranges from 1.43 to 4.10.

  2. (2)

    BCdata: The data set includes 21 instances from Barnes and Chambers35, which were acquired from the classical JSP mt10 and the la24, la40 instances. The number of jobs ranges from 10 to 15, the number of machines ranges from 11 to 18, and the flexibility of each operation ranges from 1.07 to 1.30.

  3. (3)

    HUdata: The data set includes 129 instances from Hurink et al. 36, which were obtained from 3 classical JSP instances (mt06, mt10, mt20) by Fisher and Thompson and 40 classical JSP instances (la01–la40) by Lawrence. HUdata is divided into three subsets: Edata, Rdata, and Vdata. The number of jobs ranges from 6 to 30, the number of machines ranges from 5 to 15, and the flexibility of each operation ranges from 1.15 to 7.5.

The AFSA-ED is coded and implemented in matlab language on an Intel Core i5 2.53 GHz personal computer with 1GB of RAM. The algorithm runs 30 independent times for each instance from BRdata and BCdata, and runs 10 independent times for each instance from HUdata on account of the large number of instances in this data set. The computational results are compared with several performing algorithms from the existing literatures.

Each instance can be characterized by the following parameters: number of jobs (n), number of machines (m), number of operations (T0) and the flexibility of problem (Flex). The parameters in the AFSA-ED include population size (AFs), the maximum iteration times, the try number, the step of AF (Step), the visual of AF (Visual), and the crowd factor (delta). In our experiment, the iteration times and the try number are taken as 40. The settings of the other parameters for each data set are listed in Table 3.

Data set AFs Step Visual delta
BRdata 20 5 40 10
BCdata 40 10 100 20
HUdata 60 20 200 30
Table 3.

Parameter settings of the AFSA-ED

5.2. Computational results

The computational results for each data set are shown in this subsection. In the following tables, (LB,UB) denotes the lower and upper bounds37. The LB of BRdata and BCdata instances are taken from Mastrolilli12, while the LB of HUdata instances are computed by Jurisch.38 Cm denotes the best makespan. AV denotes the average makespan. SD denotes standard deviation of the makespan. Ta is the average running time of the algorithm in terms of seconds. To illustrate the quality of the results obtained by the AFSA and the compared algorithms, the mean relative error (MRE) is also introduced. The relative error (RE) is calculated as follows: RE = (MSLB)/LB × 100%, where MS is the makespan obtained by the corresponding algorithm.

5.2.1. Influence of proposed EDA process

To investigate the influence of proposed EDA process for preying behavior, the experiments on the BRdata are conducted by implementing the AFSA-ED and the AFSA without EDA, respectively. The parameters in the AFSA are taken as the same in AFSA-ED, and the two algorithms runs 30 independent times for each instance. The results are given in Table 4. Compared with AFSA, AFSA-ED outperforms AFSA in all 10 instances for the average makespan and the best makespan, and the SD values obtained by AFSA-ED are relative smaller than AFSA for most of the instances. However, the overall computation time of the AFSA-ED is slightly longer than AFSA because of the EDA process. Fig. 7 and Fig. 8 show the convergence curves in solving MK7 and MK10 by AFSA-ED and AFSA respectively. The experiment results show the validity of the proposed EDA process for preying behavior.

Instance n × m T0 Flex. (LB,UB) ABC
HHS
AFSA
AFSA-ED
Cm AV SD Cm AV SD Cm AV SD Ta Cm AV SD Ta
Mk01 10×6 55 2.09 (36,42) 40 40.00 0.00 40 40.00 0.00 40 41.25 0.65 1.39 40 40.00 0.00 2.59
Mk02 10×6 58 4.01 (24,32) 26 26.50 0.50 26 26.63 0.49 28 29.04 0.58 1.61 26 26.10 0.30 2.82
Mk03 15×8 150 3.01 (204,211) 204 204.00 0.00 204 204.00 0.00 204 204.00 0.00 1.00 204 204.00 0.00 1.12
Mk04 15×8 90 1.91 (48,81) 60 61.22 1.36 60 60.03 1.18 64 65.51 1.03 5.68 60 60.27 0.72 12.94
Mk05 15×4 106 1.71 (168,186) 172 172.98 0.14 172 172.80 0.41 177 177.69 0.47 4.75 172 172.40 0.48 10.49
Mk06 10×15 150 3.27 (33,86) 60 64.48 1.75 58 59.13 0.63 62 63.86 0.72 20.58 57 58.60 0.75 39.27
Mk07 20×5 100 2.83 (133,157) 139 141.42 1.20 139 139.57 0.50 142 143.03 0.95 28.47 139 140.63 0.71 57.63
Mk08 20×10 225 1.43 523 523 523.00 0.00 523 523.00 0.00 523 523.00 0.00 1.04 523 523.00 0.00 2.14
Mk09 20×10 240 2.53 (299,369) 307 308.76 1.63 307 307.00 0.00 310 310.75 0.54 4.06 307 307.13 0.43 9.40
Mk10 20×15 240 2.98 (165,296) 208 212.84 2.43 205 211.13 2.37 213 214.91 1.37 50.44 201 201.93 1.06 104.10
Table 4.

Results of ten BRdata instances

Fig. 7.

Convergence curves of MK07

Fig. 8.

Convergence curves of MK10

5.2.2. Results of BRdata problems

The AFSA-ED is first tested on ten instances of BRdata. Meanwhile, we make a comparison with ABC algorithm by Wang et al.39 and HHS algorithm by Yuan et al.40. These results are also given in Table 4. It can be seen that AFSA-ED, ABC and HHS obtain the same best result for instances Mk01-Mk05, and Mk07-Mk09. For Mk06 and Mk10, AFSA-ED obtains the values of 57 and 201, respectively. On the other hand, the ABC obtains the best values of 60 and 208, respectively, and HHS obtains the best values of 58 and 205, respectively. Compared with ABC, AFSA-ED outperforms ABC in all 10 instances for the average makespan, and the SD values of AFSA-ED are relative smaller than ABC. In comparison with HHS, AFSA-ED outperforms HHS in 7 out 10 instances for the average makespan. It is worth noting that AFSA-ED can obtain average value of 201.93 and SD value of 1.06 for instance Mk10, respectively. On the other hand, the HHS can obtain average value of 211.13 and SD value of 2.37, respectively.

In addition, Table 5 gives a detailed comparison in terms of the MRE of the best value and the MRE of average value. We compare AFSA-ED with the PVNS of Yazdani et al.41, the CDDS of Ben Hmida et al.37, the BEDA of Wang et al.42, the ABC and the HHS. BKS represents the best known solution ever reported in the literature for each instance. It can be seen that AFSA-ED finds 9 best known solutions for 10 instances. The AFSA-ED obtains the MRE of the best value which is equal to 14.85%, while PVNS, CDDS, ABC, BDEA, and HHS are 16.43%, 14.98%, 16.19%, 16.07%, and 15.40%, respectively. For the MRE of average value obtained, AFSA-ED generates 15.64%, faced to 16.48% for HHS, 17.01% for PVNS, 18.55% for ABC, and 19.24 % for BDEA. However, faced to 15.34 % for the CDDS algorithm, the AFSA-ED Obtains a higher MRE. The Gantt chart of solution of MK06 obtained by AFSA-ED is showed in Fig. 9.

Instance BKS AFSA-ED
PVNS
CDDS
Cm(AV) MRE Cm(AV) MRE Cm(AV) MRE
Mk01 40 40 (40) 11.11(11.11) 40 (40) 11.11(11.11) 40 (40) 11.11(11.11)
Mk02 26 26(26.10) 8.33(8.75) 26(26.04) 8.33(8.50) 26(26) 8.33(8.33)
Mk03 204 204(204) 0.00(0.00) 204(204) 0.00(0.00) 204(204) 0.00(0.00)
Mk04 60 60(60.27) 25.00(25.56) 60(60.60) 25.00(26.25) 60(60) 25.00(25.00)
Mk05 172 172(172.40) 2.38(2.62) 173(173) 2.98(2.98) 173(173.5) 2.98(3.27)
Mk06 57 57(58.60) 72.73(77.57) 60(61) 81.82(84.85) 58(59) 75.76(78.79)
Mk07 139 139(140.63) 4.51(5.73) 141(141.2) 6.02(6.17) 139(139) 4.51(4.51)
Mk08 523 523(523) 0.00(0.00) 523(523) 0.00(0.00) 523(523) 0.00(0.00)
Mk09 307 307(307.13) 2.68(2.72) 308(308.8) 3.01(3.28) 307(307) 2.68(2.68)
Mk10 197 201(201.93) 21.82(22.38) 208(209.4) 26.06(26.91) 197(197.75) 19.39(19.85)
MRE 14.85(15.64) 16.43(17.01) 14.98(15.34)
Instance BKS ABC
BEDA
HHS
Cm(AV) MRE Cm(AV) MRE Cm(AV) MRE
Mk01 40 40 (40) 11.11(11.11) 40 (41.02) 11.11(13.94) 40 (40) 11.11(11.11)
Mk02 26 26(26.50) 8.33(10.24) 26(27.25) 8.33(13.54) 26(26.63) 8.33(10.96)
Mk03 20 204(204) 0.00(0.00) 204(204) 0.00(0.00) 204(204) 0.00(0.00)
Mk04 60 60(61.22) 25.00(27.54) 60(63.69) 25.00(32.69) 60(60.03) 25.00(25.06)
Mk05 172 172(172.98) 2.38(2.96) 173(173.38) 2.98(3.20) 172(172.80) 2.38(2.86)
Mk06 57 60(64.48) 81.82(95.39) 60(62.83) 81.82(90.39) 58(59.13) 75.76(79.18)
Mk07 139 139(141.42) 4.51(6.33) 139(141.55) 4.51(6.43) 139(139.57) 4.51(4.94)
Mk08 523 523(523) 0.00(0.00) 523(523) 0.00(0.00) 523(523) 0.00(0.00)
Mk09 307 307(308.76) 2.68(2.93) 307(310.35) 2.68(3.80) 307(307) 2.68(2.68)
Mk10 197 208(212.84) 26.06(28.99) 206(211.92) 24.85(28.44) 205(211.13) 24.24(27.96)
MRE 16.19(18.55) 16.07(19.24) 15.40(16.48)
Table 5.

Comparison between AFSA-ED and several existing algorithms on BRdata

Fig. 9.

Gantt chart of solution of MK06 obtained by AFSA-ED (makespan = 57)

To determine the statistical differences between the AFSA-ED and the compared algorithms, the Friedman test and Holm procedure are conducted. The results are presented in Table 6. It can be seen from the Friedman test results that the differences among the six algorithms are statistically relevant with 98% certainty. The AFSA-ED obtains the best overall rank. The holm procedure shows that the AFSA-ED obtains better results than the compared five algorithms, and the differences are statistically relevant with 97%, 66%, 81%, 86%, and 67% certainty, respectively.

Friedman test Holm procedure
Algorithm Rank χ2 1 − p value Diff.? Algorithm z 1 − p value
AFSA-ED 2.85 14.42 0.98 Yes - - -
PVNS 4.50 AFSA-ED v.s. PVNS 1.97 0.98
CDDS 3.20 AFSA-ED v.s. CDDS 0.41 0.66
ABC 3.60 AFSA-ED v.s. ABC 0.89 0.81
BEDA 3.75 AFSA-ED v.s. BEDA 1.07 0.86
HHS 3.10 AFSA-ED v.s. HHS 0.29 0.67
Table 6.

Friedman test and Holm procedure of different algorithms

5.2.3. Results of BCdata problems

In this subsection, we carry out experiments on 21 instances of BCdata. The detail computational results are reported and compared with the CDDS and the HDE-N1 of Yuan et al.43 in Table 7. As can be seen from Table 7, AFSA-ED outperforms CDDS and HDE-N1 in 10 out of 21instances. For the cases of seti5xxx and seti5xyz, CDDS obtains the best results of three algorithms, while AFSA-ED obtains better results than HDE-N1. The average values and SD values of AFSA-ED are better than HDE-N1. AFSA-ED offers the comparable results with HDE-N2 while being faster than HDE-N2.

Instance n × m Flex (LB,UB) CDDS HDE-N1 HDE-N2 AFSA-ED

Cm AV Cm AV SD Ta(s) Cm AV SD Ta(s) Cm AV SD Ta(s)
mt10x 10×11 1.10 (655,929) 918 918 918 922.86 6.11 21.43 918 918.58 2.20 179.22 918 918.00 0.00 23.47
mt10xx 10×12 1.20 (655,929) 918 918 918 922.04 6.31 21.70 918 918.38 1.90 179.84 918 918.53 1.35 20.91
mt10xxx 10×13 1.30 (655,936) 918 918 918 919.94 3.96 23.05 918 918.00 0.00 179.39 918 918.17 0.37 25.38
mt10xy 10×12 1.20 (655,913) 906 906 905 906.52 1.09 22.51 905 905.56 0.79 169.77 905 905.23 0.55 22.80
mt10xyz 10×13 1.30 (655,849) 849 850.5 847 856.80 3.99 21.79 847 851.14 4.65 160.24 847 851.07 2.93 24.63
mt10c1 10×11 1.10 (655,927) 928 928.5 927 928.92 1.96 21.07 927 927.72 0.45 174.19 927 927.20 0.47 23.35
mt10cc 10×12 1.20 (655,914) 910 910.75 910 913.92 3.40 21.00 908 910.60 2.40 165.61 908 908.40 1.13 40.86
setb4x 15×11 1.10 (846,937) 925 925 925 931.50 2.48 33.04 925 925.82 2.11 338.30 925 925.83 1.79 35.89
setb4xx 15×12 1.20 (847,930) 925 925 925 930.38 3.29 29.76 925 925.64 1.98 336.24 925 925.56 1.72 38.64
setb4xxx 15×13 1.30 (846,925) 925 925 925 931.42 3.59 29.89 925 925.48 1.68 353.55 925 925.60 1.45 36.42
setb4xy 15×12 1.20 (845,924) 916 916 910 921.38 4.44 31.13 910 914.00 3.50 330.18 910 913.90 2.70 36.50
setb4xyz 15×13 1.30 (838,914) 905 906.5 905 913.40 4.21 30.39 903 905.28 1.16 314.64 903 904.06 0.85 76.28
setb4c9 15×11 1.10 (857,924) 919 919 914 919.32 2.87 32.19 914 917.12 2.52 313.02 914 916.26 2.17 64.27
setb4cc 15×12 1.20 (857,909) 909 910.5 909 912.58 3.81 32.00 907 909.58 1.89 316.89 907 908.00 1.13 83.61
seti5x 15×16 1.07 (955,1218) 1201 1201.5 1204 1215.48 5.36 73.20 1200 1205.64 3.43 1112.77 1198 1202.95 2.64 153.82
seti5xx 15×17 1.13 (955,1204) 1199 1199 1202 1205.66 2.56 72.52 1197 1202.68 2.02 1078.60 1198 1201.23 1.99 93.12
seti5xxx 15×18 1.20 (955,1213) 1197 1197.5 1202 1206.10 3.18 72.07 1197 1202.26 2.37 1087.12 1197 1202.63 2.24 97.86
seti5xy 15×17 1.13 (955,1148) 1136 1138 1138 1146.86 5.04 78.98 1136 1137.98 2.82 1250.62 1136 1138.13 1.98 142.65
seti5xyz 15×18 1.20 (955,1127) 1125 1125.3 1130 1137.44 3.42 80.85 1125 1129.76 2.44 1244.22 1125 1129.53 1.76 405.74
seti5c12 15×16 1.07 (1027,1185) 1174 1174.5 1175 1182.54 7.62 69.06 1171 1175.42 1.63 1141.43 1174 1174.67 1.02 313.40
seti5cc 15×17 1.13 (955,1136) 1136 1137 1137 1145.62 5.58 78.83 1136 1137.76 2.48 1222.53 1136 1137.73 1.60 324.07
Table 7.

Comparison of AFSA-ED with CDDS and HDE-N1 on BCdata

Table 8 lists the best makespan and the MRE of AFSA-ED, TSBM2h by Bozejko et al. 13, CDDS37, IFS by Oddi et al. 44, HDE-N1 and HDE-N2 by Yuan et al.43. For the IFS algorithm, its performance depends on the relaxing factor γ, the table lists the results obtained by running IFS with γ ranging from 0.2 to 0.7, respectively. The difference between HDE-N1 and HDE-N2 is neighborhood structure. Moreover, HDE-N2 is more effective than HDE-N1, but its computational time is much longer than HDE-N1. From Table 8, as for the best makespan obtained, AFSA-ED obtains 85% of best known solutions, while TSBM2h obtains 81%, CDDS obtains 52%, IFS obtains 47%, HDE-N1 obtains 52%, and HDE-N2 obtains 95%. It can be seen that HDE-N2 outperforms AFSA-ED on two instances (seti5xxx, seti5c12), while AFSA-ED outperforms HDE-N2 on one instance (seti5x). In particular, the MRE of best makespan of AFSA is 22.39%, faced to 22.45% for TSBM2h, 22.54% for CDDS, 22.55% for HDE-N1, 23.09% for IFS (γ = 0.7), and 22.39% for HDE-N2. We note that AFSA-ED performs better than the TSBM2h, CDDS, IFS and HDE-N1, while the same with HDE-N2. However, the HDE-N2 tends to spend long time for finding best solutions. To determine the statistical differences among the AFSA-ED and the compared algorithms, the Friedman test and Holm procedure are also conducted. The results are presented in Table 9. It can be seen that the differences among the six algorithms are statistically relevant with 100% certainty. The AFSA-ED and the HDE-N2 obtain the best overall rank. The Holm procedure shows that the AFSA-ED obtains the same results with the HDE-N2. The Holm procedure also shows that the AFSA-ED obtains better results than other four algorithms, and the differences are statistically relevant with 62%, 94%, 100%, and 94%, respectively.

Instance BKS AFSA-ED TSBM2h CDDS IFS
HDE-N1 HDE-N2
0.2 0.3 0.4 0.5 0.6 0.7
mt10x 918 918 922 918 980 936 936 934 918 918 918 918
mt10xx 918 918 918 918 936 929 936 933 918 926 918 918
mt10xxx 918 918 918 918 936 929 936 926 926 926 918 918
mt10xy 905 905 905 906 922 923 923 915 905 909 905 905
mt10xyz 847 847 849 849 878 858 851 862 847 851 847 847
mt10c1 927 927 927 928 943 937 986 934 934 927 927 927
mt10cc 908 908 908 910 926 923 919 919 910 911 910 908
setb4x 925 925 925 925 967 945 930 925 937 937 925 925
setb4xx 925 925 925 925 966 931 933 925 937 929 925 925
setb4xxx 925 925 925 925 941 930 950 950 942 935 925 925
setb4xy 910 910 910 916 910 941 936 936 916 914 910 910
setb4xyz 903 903 903 905 928 909 905 905 905 905 905 903
setb4c9 914 914 914 919 926 937 926 926 920 920 914 914
setb4cc 907 907 907 909 929 917 907 914 907 909 909 907
seti5x 1198 1198 1198 1201 1210 1199 1199 1205 1207 1209 1204 1200
seti5xx 1197 1198 1197 1199 1216 1199 1205 1211 1207 1206 1202 1197
seti5xxx 1197 1197 1197 1197 1205 1206 1206 1199 1206 1206 1202 1197
seti5xy 1136 1136 1136 1136 1175 1171 1175 1166 1156 1148 1138 1136
seti5xyz 1125 1125 1128 1125 1165 1149 1130 1134 1144 1131 1130 1125
seti5c12 1171 1174 1174 1174 1196 1209 1200 1198 1198 1175 1175 1171
seti5cc 1136 1136 1136 1136 1177 1155 1162 1166 1138 1150 1137 1136
MRE 22.39 22.45 22.54 25.48 24.25 24.44 23.96 23.28 23.09 22.55 22.39
Table 8.

Comparison of results using different algorithms (AFSA-ED, TSBM2h, CDDS, IFS, HDE)

Friedman test Holm procedure
Algorithm Rank χ2 1-p value Diff.? Algorithm z 1-p value
AFSA-ED 2.76 143.05 1.00 Yes - - -
TSBM2h 3.10 AFSA-ED v.s. TSBM2h 0.33 0.62
CDDS 4.36 AFSA-ED v.s. CDDS 1.56 0.94
IFS 0.2 9.79 AFSA-ED v.s. IFS 0.2 6.86 1.00
IFS 0.3 8.88 AFSA-ED v.s. IFS 0.3 5.97 1.00
IFS 0.4 8.45 AFSA-ED v.s. IFS 0.4 5.55 1.00
IFS 0.5 7.95 AFSA-ED v.s. IFS 0.5 5.07 1.00
IFS 0.6 6.71 AFSA-ED v.s. IFS 0.6 3.85 1.00
IFS 0.7 6.83 AFSA-ED v.s. IFS 0.7 3.97 1.00
HDE-N1 4.40 AFSA-ED v.s. HDE- N1 1.60 0.94
HDE-N2 2.76 AFSA-ED v.s. HDE- N2 0.00 0.50
Table 9.

Friedman test and Holm procedure of different algorithms on BC data

5.2.4. Results of HUdata problems

This subsection shows the results of AFSA-ED for HUdata benchmark instances. Table 10 presents the MRE of the best makespan and average makespan obtained by AFSA-ED, CDDS and HDE-N1. It can be seen that AFSA can obtain the MRE of best value of 2.30%, 1.24% and 0.20% for Edata, Rdata and Vdata, respectively, while CDDS can obtain the MRE of best value of 2.32%, 1.34% and 0.12%, respectively, HED-N1 can obtain the MRE of best value of 2.35%, 1.28% and 0.26%, respectively. Compared with CDDS, AFSA-ED could obtain better results than CDDS for some instances of Edata (la16-la35), some instances of Rdata (la01-la15, la31-la40), and some instances of Vdata (la01-la05, la26-la30). For the MRE of best and average makespan, AFSA-ED outperforms CDDS for Edata and Rdata, while CDDS obtains the best result of three algorithms for Vdata. In comparison with HDE-N1, AFSA-ED can obtain better results than HDE for some instances of Edata (mt06/10/20, la21-35), some instances of Rdata (la01-10,la21-40) and some instances of Rdata (la06-10,la21-35). For the MRE of best and average makespan, AFSA-ED outperforms HDE-N1 for three datasets.

Instance n × m Edata (Flex = 1.15)
Rdata (Flex = 2.0)
Vdata (Flex ∈ [2.5,7.5])
CDDS HDE-N1 AFSA-ED CDDS HDE-N1 AFSA-ED CDDS HDE-N1 AFSA-ED
mt06/10/20 6×6
10×10
20×5
0.00 (0.05) 0.05 (0.13) 0.00 (0.08) 0.34 (0.47) 0.34 (0.45) 0.34 (0.39) 0.00 (0.00) 0.00 (0.01) 0.00 (0.00)
la01-la05 10×5 0.00 (0.73) 0.00 (0.00) 0.00 (0.00) 0.11 (0.28) 0.11 (0.31) 0.08(0.22) 0.13 (0.23) 0.04 (0.19) 0.09 (0.20)
la06-la10 15×5 0.00 (0.19) 0.00 (0.10) 0.00 (0.06) 0.03 (0.19) 0.05 (0.10) 0.02 (0.15) 0.00 (0.00) 0.03 (0.10) 0.07 (0.11)
la11-la15 20×5 0.29 (1.12) 0.29 (0.29) 0.29 (0.29) 0.02 (0.37) 0.00 (0.02) 0.00 (0.22) 0.00 (0.00) 0.00 (0.01) 0.00 (0.00)
la16-la20 10×10 0.49 (1.15) 0.02 (0.48) 0.04 (0.45) 1.64 (1.90) 1.64 (1.69) 1.64 (1.65) 0.00 (0.00) 0.00 (0.00) 0.00 (0.00)
la21-la25 15×10 5.70 (6.27) 5.82 (6.41) 5.66 (6.35) 3.82 (4.26) 3.73 (4.57) 3.68 (4.46) 0.70 (1.01) 1.63 (2.15) 1.40 (1.89)
la26-la30 20×10 3.96 (4.84) 3.89 (4.71) 3.78 (4.69) 0.66 (0.98) 1.04 (1.41) 0.97 (0.84) 0.11 (0.19) 0.42 (0.63) 0.09 (0.17)
la31-la35 30×10 0.42 (0.83) 0.50 (0.59) 0.37 (0.55) 0.22 (0.41) 0.22 (0.33) 0.18 (0.33) 0.02 (0.04) 0.12 (0.18) 0.07 (0.12)
la36-la40 15×15 9.10 (9.88) 9.63 (10.43) 9.64 (9.95) 4.85 (4.97) 3.98 (4.92) 3.89 (4.88) 0.00 (0.00) 0.00 (0.01) 0.00 (0.00)
MRE (%) 2.32 (2.91) 2.35 (2.68) 2.30 (2.60) 1.34 (1.59) 1.28 (1.59) 1.24 (1.51) 0.12 (0.16) 0.26 (0.38) 0.20 (0.29)
Table 10.

Comparison of MRE obtained by using AFSA-ED, CDDS and HDE-N1 on HUdata

5.3. Discussions

In Table 11, we summarize the MRE of the best makespan obtained by our algorithm and other known algorithm for BRdata set, BCdata set and HUdata set. The first column shows the name of data set, the second column shows the number of problems for each set, the following nine columns show the MRE of AFSA-ED, GA of Chen15, TS of Mastrolilli 12, GA of Pezzella17, CDDS, PVNS, HHS, HDE-N1 and HDE-N2. As can be seen in Table 11, HDE-N2 achieves the state-of-the-art performance on three data sets. Except for HDE-N2, AFSA-ED outperforms the other seven algorithms on BRdata and BCdata; it outperforms GA_Chen, GA_Pezzella, PVNS and HHS on three sub-data sets of HUdata, and CDDS on Edata and Rdata. TS works better than AFSA-ED on the HUdata, and CDDS works better than AFSA-ED on Vdata. In particular, HDE-N2 is a time consuming algorithm, in which the computational time is about 5 times longer than AFSA-ED as shown in Table 7. In conclusion, the results show that the AFSA-ED is an effective algorithm for FJSP.

Dada set PNum AFSA-ED GA_Chen TS GA_Pezzella CDDS PVNS HHS HDE-N1 HDE-N2
BRdata 10 14.85 19.55 19.55 17.53 14.98 16.39 15.40 15.58 14.67
BCdata 21 22.39 38.64 38.64 29.56 22.54 26.66 22.89 22.55 22.39
Hurink Edata 43 2.30 5.59 2.17 6.00 2.32 3.86 2.67 2.35 2.11
Hurink Rdata 43 1.24 4.41 1.24 4.42 1.34 1.88 1.88 1.28 1.05
Hurink Vdata 43 0. 20 2.59 0.095 2.04 0.12 0.42 0.39 0.26 0.080
Table 11.

MRE of the best makespan obtained by AFSA-ED and other known algorithms

6. Conclusion

In this paper, an efficient artificial fish swarm algorithm with estimation of distribution was proposed for solving the flexible job-shop scheduling problem with the criterion to minimize the makespan. Considering the interaction of two sub-problems, we propose the pre-principle and post-principle arranging mechanism to adjust machine assignment and operation sequence with different orders. For improving the global exploration of algorithm, we modify preying behavior with estimation of distribution and embed attracting behavior to the algorithm. To balance the exploration and exploitation, the critical path based local search was used. The proposed algorithm is tested on 160 well known benchmark instances and 121 best known solutions are found. The computational results and comparisons demonstrate that the proposed AFSA-ED outperforms several existing algorithms and is especially effective for the FJSP. In the future research, the AFSA could be used in multi-objective FJSP or many real world manufacturing systems.

Acknowledgements

The authors would like to thank the support of the National Natural Science Foundation of China (61572104, 61103146, 61402076, 61502072), Startup Fund for the Doctoral Program of Liaoning Province (20141023), the Fundamental Research Funds for the Central Universities (DUT15QY26, DUT15RC(3)088), and the project of the Key Laboratory of Symbolic Computation and Knowledge Engineering in Jilin University (93K172016K11).

References

35.JW Barnes and JB Chambers. Flexible job shop scheduling by tabu search, Graduate program in operations research and industrial engineering, the University of Texas at Austin, Technical Report Series (1996), ORP96–09
38.B Jurisch, Scheduling jobs in shops with multi-purpose machines. Thesis PhD. Fachbereich Mathematik Informatik (Universitat Osnabruck, 1992).
Journal
International Journal of Computational Intelligence Systems
Volume-Issue
9 - 5
Pages
917 - 931
Publication Date
2016/09/01
ISSN (Online)
1875-6883
ISSN (Print)
1875-6891
DOI
10.1080/18756891.2016.1237190How to use a DOI?
Copyright
© 2016. the authors. Co-published by Atlantis Press and Taylor & Francis
Open Access
This is an open access article under the CC BY-NC license (http://creativecommons.org/licences/by-nc/4.0/).

Cite this article

TY  - JOUR
AU  - Hongwei Ge
AU  - Liang Sun
AU  - Xin Chen
AU  - Yanchun Liang
PY  - 2016
DA  - 2016/09/01
TI  - An Efficient Artificial Fish Swarm Model with Estimation of Distribution for Flexible Job Shop Scheduling
JO  - International Journal of Computational Intelligence Systems
SP  - 917
EP  - 931
VL  - 9
IS  - 5
SN  - 1875-6883
UR  - https://doi.org/10.1080/18756891.2016.1237190
DO  - 10.1080/18756891.2016.1237190
ID  - Ge2016
ER  -